Work on the lodge redevelopment is rolling along nicely and results are looking great.
- The structure and roof is in place for the extension of the dining room. This includes an impressive oregon truss where the old wall used to be.
- Work has begun in remodelling the public bathroom. The toilet and shower will now have separate entrances and the finish will be similar to the en-suite bathrooms.
- The iron bark used for cladding and featured posts has a beautiful red colour. Ironbark is also being used on the new entry canopy.
- As sections of roof and cladding are completed, scaffolding is being removed. We can now see how good the new cladding and windows are looking.
- Room 15 has been extended to include the area that was a balcony. The interior panelling has been completed and nicely matches the pre-existing walls.
- The snow splitter that directs snow around the flue from the fireplace has an improved watertight mounting